Novarly ParcelRenewable sites

Renewable sitesCroome Airfield Solar Farm

Croome Airfield Solar Farm

Croome Airfield Solar Farm is an operational 49.9 MW solar farm in Wychavon, generating since 1 February 2023. Planning permission was granted on 10 July 2020, 7 months after submission. Operator of record: Croome Airfield Solar.

49.9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2023
Solar Photovoltaics
Technology
Croome Airfield Solar
Wychavon
Authority
England

Planning and build timeline

Application submitted10 December 2019
Permission granted10 July 2020
7 months after submission
Operational1 February 2023
31 months after consent

Screening a site of your own?

RedlineUK · £39

Wychavon approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Croome Airfield Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wychavon’s record on solar

Wychavon has decided 34 solar farms and approved 97%, taking a median of 4.4 months. See every solar farm decision in Wychavon

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
81.9 km
Solar Photovoltaics · Operational
322.2 km
EfW Incineration · Under Construction
56.3 km
Wind Onshore · Operational
1.38.5 km
Landfill Gas · Operational
3.49.9 km
Solar Photovoltaics · Operational
510.3 km
Solar Photovoltaics · Operational
0.3810.4 km
Solar Photovoltaics · Operational
911 km

How big is Croome Airfield Solar Farm?

Croome Airfield Solar Farm has a recorded installed capacity of 49.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Croome Airfield Solar Farm?

REPD records the operator as Croome Airfield Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Croome Airfield Solar Farm approved and built?

The application was submitted on 10 December 2019. Permission was granted on 10 July 2020, 7 months later. The site became operational on 1 February 2023, 31 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7840.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode