Renewable sites › Craigengelt
Craigengelt
Craigengelt is an operational 20 MW onshore wind farm in Stirling, generating since 31 March 2010. Planning permission was granted on 12 February 2008, 14 months after submission. Operator of record: Scotia Wind Ltd.
Planning and build timeline
| Application submitted | 1 December 2006 |
| Permission granted | 12 February 2008 14 months after submission |
| Operational | 31 March 2010 26 months after consent |
Screening a site of your own?
Stirling approves 64% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Craigengelt’s recorded coordinate — swap in your own postcode or coordinates.
Stirling’s record on onshore wind
Stirling has decided 11 onshore wind schemes and approved 64%, taking a median of 14.4 months. See every onshore wind scheme decision in Stirling →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 1.5 | 1.5 km |
Wind Onshore · Operational | 37.5 | 3.4 km |
Wind Onshore · Operational | 22.5 | 6 km |
Anaerobic Digestion · Operational | 2.4 | 11 km |
Anaerobic Digestion · Operational | 1 | 11 km |
Anaerobic Digestion · Operational | 2.4 | 11 km |
Biomass (dedicated) · Operational | 15 | 11.8 km |
Wind Onshore · Operational | 12 | 11.9 km |
How big is Craigengelt?
Craigengelt has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Craigengelt?
REPD records the operator as Scotia Wind Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Craigengelt approved and built?
The application was submitted on 1 December 2006. Permission was granted on 12 February 2008, 14 months later. The site became operational on 31 March 2010, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2940.