Craigannet Farm Wind Turbine is an operational 1.5 MW onshore wind farm in Stirling, generating since 31 March 2017. Planning permission was granted on 16 August 2015, 4 months after submission. Operator of record: Clean Earth Energy.
Planning and build timeline
| Application submitted | 27 April 2015 |
| Permission granted | 16 August 2015 4 months after submission |
| Operational | 31 March 2017 19 months after consent |
Screening a site of your own?
Stirling approves 64% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Craigannet Farm Wind Turbine’s recorded coordinate — swap in your own postcode or coordinates.
Stirling’s record on onshore wind
Stirling has decided 11 onshore wind schemes and approved 64%, taking a median of 14.4 months. See every onshore wind scheme decision in Stirling →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 20 | 1.5 km |
Wind Onshore · Operational | 37.5 | 3.3 km |
Wind Onshore · Operational | 22.5 | 5.9 km |
Anaerobic Digestion · Operational | 1 | 10.8 km |
Anaerobic Digestion · Operational | 2.4 | 10.8 km |
Anaerobic Digestion · Operational | 2.4 | 10.9 km |
Wind Onshore · Operational | 12 | 12.9 km |
Biomass (dedicated) · Operational | 15 | 13.2 km |
How big is Craigannet Farm Wind Turbine?
Craigannet Farm Wind Turbine has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Craigannet Farm Wind Turbine?
REPD records the operator as Clean Earth Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Craigannet Farm Wind Turbine approved and built?
The application was submitted on 27 April 2015. Permission was granted on 16 August 2015, 4 months later. The site became operational on 31 March 2017, 19 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6318.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode