Renewable sites › Tod Hill Farm Wind Turbines
Tod Hill Farm Wind Turbines
Tod Hill Farm Wind Turbines is operational in Falkirk with a recorded capacity of 12 MW, and has been generating since 2015-01-22.
Planning and build timeline
| Application submitted | 2011-06-17 |
| Permission granted | 2012-06-06 12 months after submission |
| Operational | 2015-01-22 32 months after consent |
Falkirk’s record on onshore wind
Falkirk has decided 5 onshore wind schemes and approved 80%, taking a median of 11.7 months. See every onshore wind scheme decision in Falkirk →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rosehill Wind Turbines Wind Onshore · Operational | 2.4 | 3.3 km |
Cowie Biomass Facility Biomass (dedicated) · Operational | 15 | 4.9 km |
Merchiston Industrial Estate, Smith Street - Battery Storage Battery · Under Construction | 43 | 5.4 km |
Carrongrange Park - Hydro Powerhouse Small Hydro · Under Construction | — | 6.8 km |
CalaChem Fine Chemicals (Grangemouth) EfW Incineration · Under Construction | 21.5 | 8.2 km |
Deerdykes Composting and Organics Recycling Facility (Waste AD) Anaerobic Digestion · Operational | 1 | 9.1 km |
Cumbernauld BioPlant (Waste AD) Anaerobic Digestion · Operational | 2.4 | 9.1 km |
Energen biogas Cumbernauld Anaerobic Digestion · Operational | 2.4 | 9.2 km |
How big is Tod Hill Farm Wind Turbines?
Tod Hill Farm Wind Turbines has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tod Hill Farm Wind Turbines?
REPD records the operator as Falkirk Tod Hill Wind Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tod Hill Farm Wind Turbines approved and built?
The application was submitted on 2011-06-17. Permission was granted on 2012-06-06, 12 months later. The site became operational on 2015-01-22, 32 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3415.