Novarly ParcelRenewable sites

Renewable sitesTod Hill Farm Wind Turbines

Tod Hill Farm Wind Turbines

Tod Hill Farm Wind Turbines is an operational 12 MW onshore wind farm in Falkirk, generating since 22 January 2015. Planning permission was granted on 6 June 2012, 12 months after submission. Operator of record: Falkirk Tod Hill Wind Limited.

12 MW
Capacity
as recorded in REPD
Operational
Status
since 22 January 2015
Wind Onshore
Technology
Falkirk Tod Hill Wind Limited
Falkirk
Authority
Scotland

Planning and build timeline

Application submitted17 June 2011
Permission granted6 June 2012
12 months after submission
Operational22 January 2015
32 months after consent

Screening a site of your own?

RedlineUK · £39

Falkirk approves 80% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tod Hill Farm Wind Turbines’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Falkirk’s record on onshore wind

Falkirk has decided 5 onshore wind schemes and approved 80%, taking a median of 11.7 months. See every onshore wind scheme decision in Falkirk

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.43.3 km
Biomass (dedicated) · Operational
154.9 km
Battery · Under Construction
435.4 km
Small Hydro · Under Construction
6.8 km
EfW Incineration · Under Construction
21.58.2 km
Anaerobic Digestion · Operational
19.1 km
Anaerobic Digestion · Operational
2.49.1 km
Anaerobic Digestion · Operational
2.49.2 km

How big is Tod Hill Farm Wind Turbines?

Tod Hill Farm Wind Turbines has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tod Hill Farm Wind Turbines?

REPD records the operator as Falkirk Tod Hill Wind Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tod Hill Farm Wind Turbines approved and built?

The application was submitted on 17 June 2011. Permission was granted on 6 June 2012, 12 months later. The site became operational on 22 January 2015, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3415.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode