Earlsburn
Earlsburn is an operational 37.5 MW onshore wind farm in Stirling, generating since 1 February 2007. Planning permission was granted on 1 July 2004, 7 months after submission. Operator of record: Falck Renewables.
Planning and build timeline
| Application submitted | 17 November 2003 |
| Permission granted | 1 July 2004 7 months after submission |
| Operational | 1 February 2007 31 months after consent |
Screening a site of your own?
Stirling approves 64% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Earlsburn’s recorded coordinate — swap in your own postcode or coordinates.
Stirling’s record on onshore wind
Stirling has decided 11 onshore wind schemes and approved 64%, taking a median of 14.4 months. See every onshore wind scheme decision in Stirling →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 22.5 | 2.7 km |
Wind Onshore · Operational | 1.5 | 3.3 km |
Wind Onshore · Operational | 20 | 3.4 km |
Anaerobic Digestion · Operational | 1 | 14.1 km |
Anaerobic Digestion · Operational | 2.4 | 14.1 km |
Anaerobic Digestion · Operational | 2.4 | 14.2 km |
Biomass (dedicated) · Operational | 15 | 14.4 km |
How big is Earlsburn?
Earlsburn has a recorded installed capacity of 37.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Earlsburn?
REPD records the operator as Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Earlsburn approved and built?
The application was submitted on 17 November 2003. Permission was granted on 1 July 2004, 7 months later. The site became operational on 1 February 2007, 31 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3201.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode