Novarly ParcelRenewable sites

Renewable sitesEarlsburn North (Kingsburn) Wind Farm

Earlsburn North (Kingsburn) Wind Farm

Earlsburn North (Kingsburn) Wind Farm is operational in Stirling with a recorded capacity of 22.5 MW, and has been generating since 2016-05-30.

22.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-05-30
Wind Onshore
Technology
Falck Renewables
Stirling
Authority
Scotland

Planning and build timeline

Application submitted2008-02-08
Permission granted2010-04-01
26 months after submission
Operational2016-05-30
74 months after consent

Stirling’s record on onshore wind

Stirling has decided 11 onshore wind schemes and approved 64%, taking a median of 14.4 months. See every onshore wind scheme decision in Stirling

Other built sites within 15 km

SiteMWDistance
Earlsburn
Wind Onshore · Operational
37.52.7 km
Craigannet Farm Wind Turbine
Wind Onshore · Operational
1.55.9 km
Craigengelt
Wind Onshore · Operational
206 km

How big is Earlsburn North (Kingsburn) Wind Farm?

Earlsburn North (Kingsburn) Wind Farm has a recorded installed capacity of 22.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Earlsburn North (Kingsburn) Wind Farm?

REPD records the operator as Falck Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Earlsburn North (Kingsburn) Wind Farm approved and built?

The application was submitted on 2008-02-08. Permission was granted on 2010-04-01, 26 months later. The site became operational on 2016-05-30, 74 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4247.

Novarly Parcel · official public data, read properly · parcel.novarly.com