Novarly ParcelRenewable sites

Renewable sitesSpring Farm (biomass)

Spring Farm (biomass)

Spring Farm (biomass) is an operational 1 MW anaerobic digestion plant in Broadland, generating since 1 August 2011. Planning permission was granted on 15 December 2009, 5 months after submission. Operator of record: Private Developer.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2011
Anaerobic Digestion
Technology
Private Developer
Broadland
Authority
England

Planning and build timeline

Application submitted16 July 2009
Permission granted15 December 2009
5 months after submission
Operational1 August 2011
20 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Broadland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Spring Farm (biomass)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
1.50.5 km
Landfill Gas · Operational
1.31.2 km
Landfill Gas · Operational
25.6 km
Solar Photovoltaics · Operational
56.2 km
Solar Photovoltaics · Under Construction
57 km
Wind Onshore · Operational
3.67 km
Solar Photovoltaics · Operational
97.1 km
Solar Photovoltaics · Operational
1.97.6 km

How big is Spring Farm (biomass)?

Spring Farm (biomass) has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Spring Farm (biomass)?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Spring Farm (biomass) approved and built?

The application was submitted on 16 July 2009. Permission was granted on 15 December 2009, 5 months later. The site became operational on 1 August 2011, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 239.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode