Novarly ParcelRenewable sites

Renewable sitesAttlebridge Landfill Site

Attlebridge Landfill Site

Attlebridge Landfill Site is operational in Broadland with a recorded capacity of 1.3 MW, and has been generating since 1997-09-01.

1.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1997-09-01
Landfill Gas
Technology
Renewable Power Generation Ltd
Broadland
Authority
England

Planning and build timeline

Application submitted1995-03-08
Permission granted1996-01-22
11 months after submission
Operational1997-09-01
19 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Spring Farm (biomass)
Anaerobic Digestion · Operational
11.2 km
Reepham Road (Waste AD)
Anaerobic Digestion · Operational
1.51.7 km
The Old Airfield
Solar Photovoltaics · Operational
55.1 km
Costessey Landfill Gas Project 2
Landfill Gas · Operational
25.5 km
Weston Airfield Wind Turbines
Wind Onshore · Operational
3.65.8 km
Woodforde Farm
Solar Photovoltaics · Operational
95.9 km
New Road Solar Farm
Solar Photovoltaics · Under Construction
57 km
Briar Solar Farm
Solar Photovoltaics · Operational
1.98.2 km

How big is Attlebridge Landfill Site?

Attlebridge Landfill Site has a recorded installed capacity of 1.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Attlebridge Landfill Site?

REPD records the operator as Renewable Power Generation Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Attlebridge Landfill Site approved and built?

The application was submitted on 1995-03-08. Permission was granted on 1996-01-22, 11 months later. The site became operational on 1997-09-01, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 509.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council