Novarly ParcelRenewable sites

Renewable sitesReepham Road (Waste AD)

Reepham Road (Waste AD)

Reepham Road (Waste AD) is operational in Broadland with a recorded capacity of 1.5 MW, and has been generating since 2012-04-30.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2012-04-30
Anaerobic Digestion
Technology
Material Change
Broadland
Authority
England

Planning and build timeline

Application submitted2010-10-28
Permission granted2011-05-25
7 months after submission
Operational2012-04-30
11 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Spring Farm (biomass)
Anaerobic Digestion · Operational
10.5 km
Attlebridge Landfill Site
Landfill Gas · Operational
1.31.7 km
Costessey Landfill Gas Project 2
Landfill Gas · Operational
25.5 km
The Old Airfield
Solar Photovoltaics · Operational
56.8 km
New Road Solar Farm
Solar Photovoltaics · Under Construction
57 km
Briar Solar Farm
Solar Photovoltaics · Operational
1.97.2 km
Weston Airfield Wind Turbines
Wind Onshore · Operational
3.67.5 km
Woodforde Farm
Solar Photovoltaics · Operational
97.6 km

How big is Reepham Road (Waste AD)?

Reepham Road (Waste AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Reepham Road (Waste AD)?

REPD records the operator as Material Change. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Reepham Road (Waste AD) approved and built?

The application was submitted on 2010-10-28. Permission was granted on 2011-05-25, 7 months later. The site became operational on 2012-04-30, 11 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 251.

Novarly Parcel · official public data, read properly · parcel.novarly.com