Novarly ParcelRenewable planning

Renewable planning Onshore windAntrim and Newtownabbey

Onshore wind planning in Antrim and Newtownabbey

Antrim and Newtownabbey has decided 19 onshore wind schemes and approved 79% of them, taking a median of 20.4 months to decide. Consented capacity: 88 MW. 3 applications still awaiting a decision.

79%
Approved
15 granted · 4 refused
20.4 mo
Median decision
UK 11.5 mo
88 MW
Consented
27 MW refused
4
Appeals
1 allowed on appeal

How Antrim and Newtownabbey compares

Against the 75 UK authorities with 5+ onshore wind decisions, Antrim and Newtownabbey sits in the 66th percentile for approval rate (11 points above the England average) and the 19th percentile for speed.

Decisions by year

35Approved — 2 (2010)210Approved — 1 (2011)111Approved — 1 (2012)Refused — 1 (2012)212Approved — 1 (2013)Refused — 1 (2013)213Approved — 1 (2015)115Approved — 1 (2017)117Approved — 1 (2018)118Approved — 1 (2019)119Approved — 1 (2020)120Approved — 3 (2022)322Refused — 1 (2024)124Approved — 1 (2025)125
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (23)

SchemeMWStatusDecided
Wind Turbine Development in Antrim
Heron Storage Limited · LA03/2024/0604/F · 10.2 mo to decide
Awaiting Construction2025-06-18
Wind Turbine Development in Ballymoney
Private Developer · LA01/2024/1005/F
0.6Application Submitted2024-08-28
Power Generation Development in Templepatrick
Private Developer · LA03/2023/0051/F · 14.9 mo to decide
0.25Application Refused2024-04-30
Budore Road, Ligoniel - Wind Turbine
Ellesmere Renewables Ltd · LA03/2024/0203/DC
Application Submitted2024-04-08
Boghill Road Wind Turbine
Hill Power Limited · LA03/2021/0136/F · 20.4 mo to decide
Awaiting Construction2022-10-24
Aughnabrack Road Replacement Turbine
Hill Power Limited · LA03/2021/0134/F · 16.9 mo to decide
Awaiting Construction2022-07-08
Wind Turbine Alterations in Randalstown
HHT Renewables Ltd · LA03/2021/1028/F · 7.2 mo to decide
0.25Awaiting Construction2022-05-27
Laurel Lane
URTV · LA03/2019/0442/F · 10.9 mo to decide
0.5Awaiting Construction2020-04-20
Boghill Road
Hill Power · LA03/2019/0272/F
2Application Withdrawn2019-11-07
Whappstown & Castlegore Windfarms
Capital Dynamics · LA02/2018/0897/F · 10.3 mo to decide
23.1Awaiting Construction2019-08-13
Lands at Ballyutoag Road
Sperrin Environmental · LA03/2016/0214/F · 26.1 mo to decide
2.3Awaiting Construction2018-08-20
Connaught Road
Connaught Wind · LA03/2017/0945/F
1.6Appeal Refused2018-01-12
Seegronan Wind Farm Extension
Seegronan Windfarm · J/2013/0187/F · 47.7 mo to decide
9Awaiting Construction2017-06-30
Ballyutoag Wind Farm
BSI Wind (formerly TCI Renewables) · T/2014/0478/F · 12.5 mo to decide
11.5Awaiting Construction2015-12-23
Castlegore Wind Farm
ABO Wind NI · G/2011/0136/F · 51.2 mo to decide
23.1Revised2015-07-15
Drumadarragh Wind Farm
Drumdarragh Windfarm Ltd · U/2005/0281/F · 101.9 mo to decide
8Appeal Refused2013-11-15
Corby Knowe
Gaelectric Developments/ CGN Europe Energy · T/2006/0832/F · 74.4 mo to decide
5Operational2013-01-30
Altgolan
Unknown · J/2006/0840/F · 68.6 mo to decide
17.5Appeal Refused2012-05-10
Connaught Road
Lowlands Health & Energy Ltd� · T/2008/0358/F · 44.9 mo to decide
1.7Operational2012-03-01
Seegronan
Seegronan Windfarm · J/2006/0883/F · 52.7 mo to decide
13.8Operational2011-01-13
Wind Turbine 1
Brett Martin Ltd · U/2009/0250/F · 8.5 mo to decide
2.3Operational2010-02-15
Carn Hill
Gaelectric Developments/ CGN Europe Energy · U/2006/0054/F · 47.8 mo to decide
13.8Operational2010-02-12
Elliot's Hill Wind Farm
B9 Energy Services Ltd/ ScottishPower Renewables · 11.2 mo to decide
5Operational1994-10-26

Does Antrim and Newtownabbey approve onshore wind schemes?

Yes — of the 19 onshore wind schemes Antrim and Newtownabbey has decided, 79% were approved (15 granted, 4 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Antrim and Newtownabbey?

The median time from application to decision is 20.4 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Antrim and Newtownabbey consented?

88 MW has been consented across 15 approved schemes, with 27 MW refused. A further 3 applications awaits a decision.

Other technologies in Antrim and Newtownabbey

Solar in Antrim and NewtownabbeyBattery storage in Antrim and Newtownabbey

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.