Novarly ParcelRenewable sites

Renewable sitesClearwell Farm - solar

Clearwell Farm - solar

Clearwell Farm - solar is an operational 2 MW solar farm in Newport, generating since 15 December 2015. Planning permission was granted on 20 May 2011, 1 months after submission. Operator of record: Heritage Energy.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2015
Solar Photovoltaics
Technology
Heritage Energy
Newport
Authority
Wales

Planning and build timeline

Application submitted7 April 2011
Permission granted20 May 2011
1 months after submission
Operational15 December 2015
55 months after consent

Screening a site of your own?

RedlineUK · £39

Newport approves 85% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Clearwell Farm - solar’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Newport’s record on solar

Newport has decided 13 solar farms and approved 85%, taking a median of 6.6 months. See every solar farm decision in Newport

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.91.4 km
Fuel Cell (Hydrogen) · Under Construction
0.115.2 km
Battery · Under Construction
1.085.2 km
Landfill Gas · Operational
25.9 km
Wind Onshore · Operational
2.36.2 km
Solar Photovoltaics · Operational
56.7 km
Solar Photovoltaics · Operational
1.57.1 km
Landfill Gas · Operational
47.4 km

How big is Clearwell Farm - solar?

Clearwell Farm - solar has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Clearwell Farm - solar?

REPD records the operator as Heritage Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Clearwell Farm - solar approved and built?

The application was submitted on 7 April 2011. Permission was granted on 20 May 2011, 1 months later. The site became operational on 15 December 2015, 55 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1577.