Novarly ParcelRenewable planning

Renewable planning SolarNewport

Solar planning in Newport

Newport has decided 13 solar farms and approved 85% of them, taking a median of 6.6 months to decide. Consented capacity: 28 MW. 1 application still awaiting a decision.

85%
Approved
11 granted · 2 refused
6.6 mo
Median decision
UK 2.3 mo
28 MW
Consented
9 MW refused
2
Appeals
1 allowed on appeal

How Newport compares

Against the 298 UK authorities with 5+ solar decisions, Newport sits in the 15th percentile for approval rate (8 points below the England average) and the 2nd percentile for speed.

Decisions by year

35Approved — 2 (2011)211Approved — 2 (2015)Refused — 1 (2015)315Approved — 1 (2016)Refused — 1 (2016)216Approved — 1 (2021)121Approved — 1 (2023)123Approved — 3 (2024)324
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (18)

SchemeMWStatusDecided
Hasbro Bradley UK, Caswell Way - Solar PV system
Hasbro UK Limited · 24/0631 · 0.5 mo to decide
0.15Awaiting Construction2024-10-03
Docks Way - Solar Panels
Newport City Council · 23/0989 · 19.1 mo to decide
1.01Awaiting Construction2024-08-07
Celtic Way, Celtic Lakes - Solar Array
NHS Wales Shared Services Partnership (University Hospital Of Wales) · 23/1083 · 2.3 mo to decide
0.29Awaiting Construction2024-02-15
New Venture Buildings, Caswell Way - Solar Array
Bisley Office Equipment Limited · 23/0019 · 2.1 mo to decide
1.8Awaiting Construction2023-03-16
Began Road - Ground Mounted Solar Pv array
Haygrove Limited · 22/0048
0.19Application Withdrawn2022-09-19
Docks Way Solar Farm
Newport City Council · 21/0346 · 8.2 mo to decide
2.37Awaiting Construction2021-12-01
Eastern Site
Lightsource Renewable Energy · 15/0903 · 6.6 mo to decide
5Application Refused2016-02-08
Land to North West of Lodge Farm (Park Farm)
Lightsource Renewable Energy · 15/0902 · 6.6 mo to decide
4Operational2016-02-08
Land To West Of Cefn Llogell Farm
Private Developer · 15/0393 · 5.6 mo to decide
3.8Appeal Refused2015-11-04
Newport (Began Road)
Eco Energy World · 14/0337 · 18.6 mo to decide
4.9Operational2015-10-22
Court Farm
BE Renewables · 14/1275 · 7.2 mo to decide
8.5Operational2015-10-09
Coal Pit Lane
Phoenix Capital R-Energy Ltd · 14/0531
5.3Application Withdrawn2014-10-13
Court Farm
Private Developer · 13/1203 · 10.5 mo to decide
8.5Revised2014-10-01
Langstone Court Road Solar Farm
Private Developer · 11/0311 · 7.5 mo to decide
2.5Operational2011-11-09
Clearwell Farm - solar
Heritage Energy · 11/0339 · 1.4 mo to decide
2Operational2011-05-20
Imperial Park - Solar Panels
NHS Wales Shared Services Partnership (University Hospital Of Wales)
No Application Required
Kingsway Multi Storey Car Park, Newport, South Wales - Solar PV Array
Newport Norse
No Application Required
Geraint Thomas National Velodrome - Solar
Egni Co-op / Joju Sola
Operational

Does Newport approve solar farms?

Yes — of the 13 solar farms Newport has decided, 85% were approved (11 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Newport?

The median time from application to decision is 6.6 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Newport consented?

28 MW has been consented across 11 approved schemes, with 9 MW refused. A further 1 application awaits a decision.

Other technologies in Newport

Battery storage in NewportOnshore wind in Newport

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.