Renewable sitesDocksway Landfill Scheme

Docksway Landfill Scheme

Docksway Landfill Scheme is an operational 2 MW landfill gas site in Newport, generating since 30 March 2000. Planning permission was granted on 19 May 1999, 2 months after submission. Operator of record: Renewable Power Systems.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2000
Landfill Gas
Technology
Renewable Power Systems
Newport
Authority
Wales

Planning and build timeline

Application submitted23 March 1999
Permission granted19 May 1999
2 months after submission
Operational30 March 2000
10 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Newport: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Docksway Landfill Scheme’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.32.2 km
Battery · Operational
202.7 km
Biomass (dedicated) · Operational
92.9 km
Wind Onshore · Operational
52.9 km
Wind Onshore · Operational
2.53.4 km
Solar Photovoltaics · Operational
3.5 km
Battery · Under Construction
1203.6 km
Biomass (co-firing) · Operational
184.1 km

How big is Docksway Landfill Scheme?

Docksway Landfill Scheme has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Docksway Landfill Scheme?

REPD records the operator as Renewable Power Systems. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Docksway Landfill Scheme approved and built?

The application was submitted on 23 March 1999. Permission was granted on 19 May 1999, 2 months later. The site became operational on 30 March 2000, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 756.