Novarly ParcelRenewable sites

Renewable sitesCairnmore Solar Park

Cairnmore Solar Park

Cairnmore Solar Park is operational in Aberdeenshire with a recorded capacity of 3.8 MW, and has been generating since 2016-02-17.

3.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-02-17
Solar Photovoltaics
Technology
GPV Rhynie
Aberdeenshire
Authority
Scotland

Planning and build timeline

Application submitted2014-11-13
Permission granted2015-02-05
3 months after submission
Operational2016-02-17
12 months after consent

Aberdeenshire’s record on solar

Aberdeenshire has decided 39 solar farms and approved 100%, taking a median of 2.1 months. See every solar farm decision in Aberdeenshire

Other built sites within 15 km

SiteMWDistance
Cairnmore Solar Park (extension)
Solar Photovoltaics · Operational
1.20.2 km
Cairnmore Farm
Wind Onshore · Operational
2.61.1 km
Upper Wheedlemont Farm
Wind Onshore · Operational
1.73.3 km
Clashindarroch
Wind Onshore · Operational
376.9 km
Kildrummy Windfarm
Wind Onshore · Operational
18.411.9 km
Hill of Tillymorgan (Kirkton Farm) Wind turbines
Wind Onshore · Operational
9.613.6 km

How big is Cairnmore Solar Park?

Cairnmore Solar Park has a recorded installed capacity of 3.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cairnmore Solar Park?

REPD records the operator as GPV Rhynie. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cairnmore Solar Park approved and built?

The application was submitted on 2014-11-13. Permission was granted on 2015-02-05, 3 months later. The site became operational on 2016-02-17, 12 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4780.

Novarly Parcel · official public data, read properly · parcel.novarly.com