Solar planning in Bath and North East Somerset

Bath and North East Somerset has decided 17 solar farms and approved 76% of them, taking a median of 3.9 months to decide. Consented capacity: 85 MW. 3 applications still awaiting a decision.

76%
Approved
13 granted · 4 refused
3.9 mo
Median decision
UK 2.3 mo
85 MW
Consented
44 MW refused
1
Appeals
0 allowed on appeal

How Bath and North East Somerset compares

Against the 298 UK authorities with 5+ solar decisions, Bath and North East Somerset sits in the 5th percentile for approval rate (17 points below the England average) and the 16th percentile for speed.

Decisions by year

510Refused — 1 (2013)113Approved — 2 (2014)Refused — 1 (2014)314Refused — 1 (2015)115Approved — 1 (2022)122Approved — 1 (2023)123Approved — 3 (2024)324Approved — 5 (2025)Refused — 1 (2025)625
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (20)

SchemeMWStatusDecided
LiveWest Homes - Solar Panels
LiveWest Homes · 26/00907/CLPU
Application Submitted2026-03-10
Gypsy Lane, Burnett - Solar PV Arrays
Conrad Energy (Developments) Limited · 24/02489/EFUL · 14.8 mo to decide
24.5Application Refused2025-09-25
Fairy Hill, Compton Dando - Solar Farm
Environmental Gain Limited / Bath & West Community Energy Limited · 23/04529/FUL · 19.8 mo to decide
2.1Awaiting Construction2025-07-29
Stowey Road, Stowey - Solar Farm
Regener8 Power · 24/04156/EFUL · 8.6 mo to decide
49.9Awaiting Construction2025-07-24
East Dundry Lane, Norton Hawkfield - Solar Panels
Enviromena · 25/02595/FUL
15Application Submitted2025-07-02
Parcel 2882, Water Lane - Solar Farm
Pathfinder Clean Energy UK Dev Limited · 24/03894/FUL · 7.6 mo to decide
9.2Awaiting Construction2025-06-05
Royal United Hospital, Combe Park - Solar Panels
Royal United Hospital NHS Trust · 25/00838/SOLPA · 1.7 mo to decide
0.31Awaiting Construction2025-04-25
Paulton House, Old Mills - Solar Panels
Jane Clayton & Company · 24/04376/SOLPA · 2.3 mo to decide
0.19Awaiting Construction2025-02-03
Bath Sports And Leisure Centre, North Parade Road - Solar PV Panels
Bath & North East Somerset Council · 24/03026/CLPU · 2.2 mo to decide
Under Construction2024-10-14
Wellsway School, Chandag Road - PV Arrays
Bath & West Community Energy · 24/02807/SOLPA · 1.8 mo to decide
0.15Awaiting Construction2024-09-17
Bridges Electrical Engineers, Second Avenue - Solar Panels
Bridges Limited · 24/00157/SOLPA · 1.4 mo to decide
0.32Awaiting Construction2024-02-26
Optima Products, Mill Road - Solar Panels
Optima Products Limited · 23/00834/SOLPA · 1.7 mo to decide
0.3Awaiting Construction2023-05-04
King Edwards School, North Road - Solar Panels
King Edwards School · 23/01547/SOLPA
0.22Under Construction2023-04-26
Marksbury Plain - Solar Park
Renewable Connections Developments Limited · 21/04881/FUL · 5.5 mo to decide
15Awaiting Construction2022-07-01
Howgrove Farm
Green Switch Solutions · 14/03990/FUL · 8.6 mo to decide
4.7Appeal Refused2015-06-11
Chelwood Solar Farm
Mongoose Energy Coop · 14/01895/FUL · 3.8 mo to decide
5Operational2014-09-12
Hunstrete (Wilmington Farm)
Bath & West Community Energy Ltd · 14/00424/FUL · 4.4 mo to decide
2.3Operational2014-06-24
The Flatts
Camborne Energy Investments (10) Ltd · 14/01510/FUL · 2.5 mo to decide
6.8Application Refused2014-06-09
The Flats
Camborne Energy Investments (10) Ltd · 13/02527/FUL
6.8Revised2013-10-02
Wilmington Farm
TGC Renewables · 12/04345/FUL · 3.9 mo to decide
7.6Application Refused2013-02-14

Does Bath and North East Somerset approve solar farms?

Yes — of the 17 solar farms Bath and North East Somerset has decided, 76% were approved (13 granted, 4 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Bath and North East Somerset?

The median time from application to decision is 3.9 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Bath and North East Somerset consented?

85 MW has been consented across 13 approved schemes, with 44 MW refused. A further 3 applications awaits a decision.

Other technologies in Bath and North East Somerset

Battery storage in Bath and North East SomersetOnshore wind in Bath and North East Somerset

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.