Renewable sites › Chelveston Airfield
Chelveston Airfield
Chelveston Airfield is operational in Bedford with a recorded capacity of 16 MW, and has been generating since 2014-02-28.
Planning and build timeline
| Application submitted | 2012-12-19 |
| Permission granted | 2013-04-25 4 months after submission |
| Operational | 2014-02-28 10 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bedford’s record on solar
Bedford has decided 28 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Bedford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Chelveston Renewable Energy Park - Solar Extension Solar Photovoltaics · Operational | 19.5 | 0.3 km |
Chelveston Airfield - extension Solar Photovoltaics · Operational | 3.5 | 0.4 km |
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire) Wind Onshore · Operational | 12.5 | 0.8 km |
Chelveston Renewable Energy Park Battery · Under Construction | 20 | 1 km |
Chelveston Renewable Energy Park Wind Farm (Bedford) Wind Onshore · Operational | 10 | 1 km |
Westwood AD Plant (Farm AD) Anaerobic Digestion · Operational | 2 | 5.2 km |
Glebe Farm Solar Energy Park Solar Photovoltaics · Operational | 15 | 7.1 km |
Manor Farm - Pertenhall Solar Photovoltaics · Operational | 15 | 8 km |
How big is Chelveston Airfield?
Chelveston Airfield has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chelveston Airfield?
REPD records the operator as Chelveston Renewable Energy Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chelveston Airfield approved and built?
The application was submitted on 2012-12-19. Permission was granted on 2013-04-25, 4 months later. The site became operational on 2014-02-28, 10 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1949.