Glebe Farm Solar Energy Park

Glebe Farm Solar Energy Park is an operational 15 MW solar farm in Bedford, generating since 31 March 2015. Planning permission was granted on 3 June 2013, 4 months after submission. Operator of record: Vento Ludens.

15 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2015
Solar Photovoltaics
Technology
Vento Ludens
Bedford
Authority
England

Planning and build timeline

Application submitted5 February 2013
Permission granted3 June 2013
4 months after submission
Operational31 March 2015
22 months after consent

Screening a site of your own?

RedlineUK · £39

Bedford approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Glebe Farm Solar Energy Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bedford’s record on solar

Bedford has decided 28 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Bedford

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
22.1 km
Wind Onshore · Operational
8.62.3 km
Solar Photovoltaics · Operational
16.82.4 km
Solar Photovoltaics · Operational
4.66.1 km
Solar Photovoltaics · Operational
266.3 km
Wind Onshore · Operational
12.56.5 km
Solar Photovoltaics · Operational
19.57.1 km
Wind Onshore · Operational
107.1 km

How big is Glebe Farm Solar Energy Park?

Glebe Farm Solar Energy Park has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glebe Farm Solar Energy Park?

REPD records the operator as Vento Ludens. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glebe Farm Solar Energy Park approved and built?

The application was submitted on 5 February 2013. Permission was granted on 3 June 2013, 4 months later. The site became operational on 31 March 2015, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2352.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode