Glebe Farm Solar Energy Park is operational in Bedford with a recorded capacity of 15 MW, and has been generating since 2015-03-31.

15 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-31
Solar Photovoltaics
Technology
Vento Ludens
Bedford
Authority
England

Planning and build timeline

Application submitted2013-02-05
Permission granted2013-06-03
4 months after submission
Operational2015-03-31
22 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bedford’s record on solar

Bedford has decided 28 solar farms and approved 93%, taking a median of 2.7 months. See every solar farm decision in Bedford

Other built sites within 15 km

SiteMWDistance
Westwood AD Plant (Farm AD)
Anaerobic Digestion · Operational
22.1 km
Airfield Farm (Podington)
Wind Onshore · Operational
8.62.3 km
Odell Glebe Solar Farm
Solar Photovoltaics · Operational
16.82.4 km
Little Irchester, Higham Road Solar Farm
Solar Photovoltaics · Operational
4.66.1 km
London Road, Irchester - Solar Farm
Solar Photovoltaics · Operational
266.3 km
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)
Wind Onshore · Operational
12.56.5 km
Chelveston Renewable Energy Park - Solar Extension
Solar Photovoltaics · Operational
19.57.1 km
Chelveston Renewable Energy Park Wind Farm (Bedford)
Wind Onshore · Operational
107.1 km

How big is Glebe Farm Solar Energy Park?

Glebe Farm Solar Energy Park has a recorded installed capacity of 15 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glebe Farm Solar Energy Park?

REPD records the operator as Vento Ludens. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glebe Farm Solar Energy Park approved and built?

The application was submitted on 2013-02-05. Permission was granted on 2013-06-03, 4 months later. The site became operational on 2015-03-31, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2352.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council