Novarly ParcelRenewable sites

Renewable sitesWestwood AD Plant (Farm AD)

Westwood AD Plant (Farm AD)

Westwood AD Plant (Farm AD) is operational in North Northamptonshire with a recorded capacity of 2 MW, and has been generating since 2009-06-30.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2009-06-30
Anaerobic Digestion
Technology
Ancala Bioenergy (formerly Biogen)
North Northamptonshire
Authority
England

Planning and build timeline

Application submitted2008-01-11
Permission granted2008-05-15
4 months after submission
Operational2009-06-30
14 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Glebe Farm Solar Energy Park
Solar Photovoltaics · Operational
152.1 km
Odell Glebe Solar Farm
Solar Photovoltaics · Operational
16.84.1 km
Airfield Farm (Podington)
Wind Onshore · Operational
8.64.2 km
Chelveston Renewable Energy Park Wind Farm (East Northamptonshire)
Wind Onshore · Operational
12.54.7 km
Chelveston Airfield
Solar Photovoltaics · Operational
165.2 km
Chelveston Renewable Energy Park - Solar Extension
Solar Photovoltaics · Operational
19.55.2 km
Chelveston Airfield - extension
Solar Photovoltaics · Operational
3.55.4 km
Chelveston Renewable Energy Park Wind Farm (Bedford)
Wind Onshore · Operational
105.4 km

How big is Westwood AD Plant (Farm AD)?

Westwood AD Plant (Farm AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Westwood AD Plant (Farm AD)?

REPD records the operator as Ancala Bioenergy (formerly Biogen). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Westwood AD Plant (Farm AD) approved and built?

The application was submitted on 2008-01-11. Permission was granted on 2008-05-15, 4 months later. The site became operational on 2009-06-30, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 272.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council