Solar planning in Carmarthenshire

Carmarthenshire has decided 28 solar farms and approved 93% of them, taking a median of 4.8 months to decide. Consented capacity: 123 MW. 5 applications still awaiting a decision.

93%
Approved
26 granted · 2 refused
4.8 mo
Median decision
UK 2.3 mo
123 MW
Consented
5 MW refused
0
Appeals
no appeals recorded

How Carmarthenshire compares

Against the 298 UK authorities with 5+ solar decisions, Carmarthenshire sits in the 35th percentile for approval rate (level with the England average) and the 9th percentile for speed.

Decisions by year

510Approved — 2 (2011)211Approved — 1 (2012)112Approved — 6 (2013)613Approved — 2 (2014)214Approved — 5 (2015)515Approved — 1 (2016)Refused — 1 (2016)216Refused — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2024)124Approved — 5 (2025)525Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (36)

SchemeMWStatusDecided
Ty Cwm Gwendraeth, Gwalia Mynydd Mawr - Solar Panels
Ty Cwm Gwendraeth Limited · PL/10440 · 0.6 mo to decide
Awaiting Construction2026-02-13
Brecon Beacon Natural Water - Ground Mounted Solar Panels
Brecon Carreg Limited · 24/23206/FUL · 13.1 mo to decide
0.6Awaiting Construction2025-12-16
Dyfed Powys Police Headquarters, Llangunnor Road - Solar Panels
Dyfed Powys Police · PL/09719 · 2 mo to decide
Awaiting Construction2025-10-02
Sandy Road - Solar Panels & Biomass Boiler
CEM Day Limited · PL/05424 · 24 mo to decide
0.22Awaiting Construction2025-03-03
Glyngwernen Farm, Uchaf Fawr - Solar Farm
Bartypower Limited · PL/08017 · 7.1 mo to decide
8.36Awaiting Construction2025-02-17
Y Tyddyn Teg, Heol Y Nant - Solar Farm
Power on Demand Limited · PL/07775 · 7.9 mo to decide
1Awaiting Construction2025-01-29
Nantycaws Waste Management Facility, Llanddarog - Solar Farm
CWM Environmental Limited (head offfice) · PL/08219 · 3.5 mo to decide
2Awaiting Construction2024-12-17
MOD Pendine, Llanmiloe - Solar Panels
QinetiQ · PL/07023
0.8Application Submitted2023-12-18
Pembrey Road - Ground Mounted Solar Panels
Gravells Limited · PL/05836
1Application Submitted2023-05-23
Morrisons Supermarket, -Solar Panels
Morrisons · PL/04895 · 1.8 mo to decide
0.41Awaiting Construction2022-12-21
Bwlchgwnt Solar Park
YnNi Teg Cyf · PL/03717 · 3.3 mo to decide
0.6Awaiting Construction2022-07-04
Morfa Pingett Solar Farm
Richard Thomas and Co (Hydro) Limited · PL/02407 · 1.5 mo to decide
1.6Application Refused2021-10-04
St Davids Park - Solar Farm
Hywel Dda University Health Board · PL/01905
Application Submitted2021-05-20
Morfa Pingett
Richard Thomas Associates · S/40618 · 9.7 mo to decide
1.6Revised2021-03-11
Morfa Ynys Farmlands
Energi Generation (formerly Solar Park Developments) · S/32892 · 6.1 mo to decide
3Planning Permission Expired2016-05-03
New Lodge Farm - Solar
Clean Power Properties · S/29559 · 24 mo to decide
3Application Refused2016-02-05
Pistyllgwyn Farm
Power for Wales Inc · W/32460 · 4.5 mo to decide
1.5Planning Permission Expired2015-12-21
Dura Park Bynea Industrial Site
Short Bros Homes · S/32873 · 1.8 mo to decide
1.4Operational2015-12-15
Parc Cynog
Vattenfall · W/32580 · 3 mo to decide
5Operational2015-11-10
Rhas Fach Farm
Power for Wales Inc · W/32377 · 2.3 mo to decide
1.2Planning Permission Expired2015-09-30
Bryncoch Solar Farm
Green Energy UK Direct · W/32171 · 2.9 mo to decide
19Abandoned2015-09-11
Land South Of Bryn Cyrnau Isaf
Green Switch Solutions - Liquidated · W/31690 · 3 mo to decide
5.9Operational2015-06-09
Bryn Cyrnau Isaf
Green Switch Developments · W/30204 · 6.9 mo to decide
6Revised2014-12-19
Redcourt Farm
PS Renewables · W/30060 · 5.2 mo to decide
3.3Operational2014-10-07
Blaen Bowi Solar park
Novus Solar Developments · W/28837 · 8.1 mo to decide
8Abandoned2014-05-14
Brynteg Farm
Brynteg Solar · S/28898 · 5.7 mo to decide
16.2Operational2014-03-11
Clawdd Ddu PV
Elgin Energy EsCo · S/27987 · 6.4 mo to decide
13.5Operational2013-10-07
Pen Y Cae solar farm
Rockfire Capital · E/28086 · 5.1 mo to decide
6.9Operational2013-09-19
Saron Road solar park
Anesco · E/28054 · 5.3 mo to decide
6.7Operational2013-09-19
Cefn Betingau Farm
Wessex Solar Energy · 2013/0865 · 2.6 mo to decide
9Operational2013-08-28
Pentre farm
Kinetica Solar · S/27526 · 2.7 mo to decide
5.5Operational2013-03-11
Caeremlyn Solar Farm
Munich RE · W/26672 · 7.5 mo to decide
18Operational2013-01-14
Blaen Bowi
Novus Solar Developments · W/26003 · 1.2 mo to decide
5.7Planning Permission Expired2012-02-24
Pont Andrew Solar Farm
Lightsource Renewable Energy · S/24069 · 4.7 mo to decide
1.5Operational2011-04-22
Ffos Las Racecourse
Private Developer · S/24039 · 5 mo to decide
5.5Operational2011-04-22
The Lord Arthur Rank Centre, Trostre Road - Installation of Solar Panels
The Foothold Group
No Application Required

Does Carmarthenshire approve solar farms?

Yes — of the 28 solar farms Carmarthenshire has decided, 93% were approved (26 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Carmarthenshire?

The median time from application to decision is 4.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Carmarthenshire consented?

123 MW has been consented across 26 approved schemes, with 5 MW refused. A further 5 applications awaits a decision.

Other technologies in Carmarthenshire

Battery storage in CarmarthenshireOnshore wind in Carmarthenshire

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.