Langford Solar Farm

Langford Solar Farm is operational in Central Bedfordshire with a recorded capacity of 13 MW, and has been generating since 2015-03-31.

13 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-31
Solar Photovoltaics
Technology
Lark Energy
Central Bedfordshire
Authority
England

Planning and build timeline

Application submitted2013-06-28
Permission granted2013-09-24
3 months after submission
Operational2015-03-31
18 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Central Bedfordshire’s record on solar

Central Bedfordshire has decided 32 solar farms and approved 97%, taking a median of 3.2 months. See every solar farm decision in Central Bedfordshire

Other built sites within 15 km

SiteMWDistance
Langford Wind Farm
Wind Onshore · Operational
202.1 km
Arlesey Landfill Gas (Extension)
Landfill Gas · Operational
2.34.3 km
Arlesey Landfill Site
Landfill Gas · Operational
1.14.6 km
Hitchin
Landfill Gas · Operational
1.57.7 km
Bygrave Lodge Farm Anaerobic Digestion Facility (Farm AD)
Anaerobic Digestion · Operational
2.38.7 km
Waterloo solar park
Solar Photovoltaics · Operational
14.612.1 km
Bassingbourn Solar Farm
Solar Photovoltaics · Operational
14.414.8 km
Vine Farm Solar Park
Solar Photovoltaics · Operational
4514.9 km

How big is Langford Solar Farm?

Langford Solar Farm has a recorded installed capacity of 13 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Langford Solar Farm?

REPD records the operator as Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Langford Solar Farm approved and built?

The application was submitted on 2013-06-28. Permission was granted on 2013-09-24, 3 months later. The site became operational on 2015-03-31, 18 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2357.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council