Renewable sites › Boardinghouse Wind Farm
Boardinghouse Wind Farm
Boardinghouse Wind Farm is operational in Fenland with a recorded capacity of 10.3 MW, and has been generating since 2015-10-01.
Planning and build timeline
| Application submitted | 2009-08-20 |
| Permission granted | 2011-07-06 23 months after submission |
| Operational | 2015-10-01 51 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Fenland’s record on onshore wind
Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ranson Moor Wind Farm (Phase 2) Wind Onshore · Operational | 4 | 3.1 km |
Ranson Moor (phase 1) Wind Onshore · Operational | 6 | 3.2 km |
Fenmarc Fenland AD Plant (Waste AD) Anaerobic Digestion · Operational | 1.5 | 3.7 km |
Asksham Community Village Solar Farm Solar Photovoltaics · Under Construction | 0.15 | 3.8 km |
Long Hill Road Wind Onshore · Operational | 2 | 4.7 km |
Greenvale AP Wind Turbine Wind Onshore · Operational | 1.5 | 4.7 km |
Stags Holt Extension Wind Onshore · Operational | 2 | 5.7 km |
Stags Holt Wind Onshore · Operational | 18 | 5.7 km |
How big is Boardinghouse Wind Farm?
Boardinghouse Wind Farm has a recorded installed capacity of 10.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Boardinghouse Wind Farm?
REPD records the operator as Ecogen. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Boardinghouse Wind Farm approved and built?
The application was submitted on 2009-08-20. Permission was granted on 2011-07-06, 23 months later. The site became operational on 2015-10-01, 51 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4345.