Ranson Moor (phase 1)

Ranson Moor (phase 1) is an operational 6 MW onshore wind farm in Fenland, generating since 1 May 2007. Planning permission was granted on 25 April 2005, 21 months after submission. Operator of record: Fenpower Limited.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 1 May 2007
Wind Onshore
Technology
Fenpower Limited
Fenland
Authority
England

Planning and build timeline

Application submitted31 July 2003
Permission granted25 April 2005
21 months after submission
Operational1 May 2007
24 months after consent

Screening a site of your own?

RedlineUK · £39

Fenland approves 85% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Ranson Moor (phase 1)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Fenland’s record on onshore wind

Fenland has decided 20 onshore wind schemes and approved 85%, taking a median of 12.8 months. See every onshore wind scheme decision in Fenland

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
40.5 km
Solar Photovoltaics · Under Construction
0.151.7 km
Wind Onshore · Operational
1.52.6 km
Wind Onshore · Operational
10.33.2 km
Solar Photovoltaics · Operational
4.74.3 km
Solar Photovoltaics · Operational
54.4 km
Wind Onshore · Operational
65.2 km
Solar Photovoltaics · Operational
4.66.2 km

How big is Ranson Moor (phase 1)?

Ranson Moor (phase 1) has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Ranson Moor (phase 1)?

REPD records the operator as Fenpower Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Ranson Moor (phase 1) approved and built?

The application was submitted on 31 July 2003. Permission was granted on 25 April 2005, 21 months later. The site became operational on 1 May 2007, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2952.