Onshore wind planning in Falkirk

Falkirk has decided 5 onshore wind schemes and approved 80% of them, taking a median of 11.7 months to decide. Consented capacity: 46 MW. 3 applications still awaiting a decision.

80%
Approved
4 granted · 1 refused
11.7 mo
Median decision
UK 11.5 mo
46 MW
Consented
4 MW refused
2
Appeals
2 allowed on appeal

⚠️ Small caseload (5 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Falkirk compares

Against the 75 UK authorities with 5+ onshore wind decisions, Falkirk sits in the 72nd percentile for approval rate (12 points above the England average) and the 62nd percentile for speed.

Decisions by year

35Approved — 1 (2012)112Approved — 1 (2013)113Approved — 1 (2022)122
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (10)

SchemeMWStatusDecided
Easter Drumclair Wood
Tamani · P/22/0086/FUL · 1.4 mo to decide
6Awaiting Construction2022-04-08
Easter Drumclair Wood
Tamani · P/21/0242/FUL
4Revised2021-04-28
Easter Drumclair Wood
Tamani · P/19/0183/FUL
4Revised2019-03-25
Easter Drumclair Wood
Tamani · P/19/0023/FUL
4Revised2019-03-13
Greenhill Farm
Tamani · P/17/0411/FUL
2Application Withdrawn2017-09-01
Burnhead
Wind Prospect Developments/ EDF · P/10/0857/FUL · 33.7 mo to decide
26Operational2013-10-08
Rullie Community Windfarm
Community Windpower · P/11/0800/FUL
25Application Withdrawn2012-09-28
Tod Hill Farm Wind Turbines
Falkirk Tod Hill Wind Limited · P/11/0326/FUL · 11.7 mo to decide
12Operational2012-06-06
ASDA Distribution Centre
Asda · P/07/0084/FUL - P/08/0511/FUL · 15.2 mo to decide
2Planning Permission Expired2009-03-04
Asda Grangemouth Depot
Asda · P/07/0084/FUL · 10.4 mo to decide
4Application Refused2007-12-20

Does Falkirk approve onshore wind schemes?

Yes — of the 5 onshore wind schemes Falkirk has decided, 80% were approved (4 granted, 1 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Falkirk?

The median time from application to decision is 11.7 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Falkirk consented?

46 MW has been consented across 4 approved schemes, with 4 MW refused. A further 3 applications awaits a decision.

Other technologies in Falkirk

Solar in FalkirkBattery storage in Falkirk

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.