Renewable sites › Oriel High School
Oriel High School
Oriel High School is operational in Crawley with a recorded capacity of 0.19 MW, and has been generating since 2021-11-10.
Planning and build timeline
| Application submitted | 2021-01-11 |
| Permission granted | 2021-03-04 2 months after submission |
| Operational | 2021-11-10 8 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Crawley’s record on solar
Crawley has decided 10 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Crawley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Majors Hill/Turners Hill Solar Farm Solar Photovoltaics · Operational | 1.1 | 3.5 km |
South Terminal Car Park Forecourt - Electric Vehicle Charging Forecourt Battery · Under Construction | — | 7.3 km |
Brookhurst Wood Gas to Energy Landfill Gas · Operational | 5.1 | 11.8 km |
Brookhurst Wood (Waste AD) Anaerobic Digestion · Operational | 4.5 | 11.8 km |
Capel Landfill Landfill Gas · Operational | 1 | 12.2 km |
Worsted Farm Solar Photovoltaics · Operational | 5 | 12.3 km |
Land At Chiddinglye Farm Solar Photovoltaics · Operational | 5 | 13.5 km |
Broockhurst Wood Landfill Gas · Operational | 2 | 13.7 km |
How big is Oriel High School?
Oriel High School has a recorded installed capacity of 0.19 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Oriel High School?
REPD records the operator as West Sussex County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Oriel High School approved and built?
The application was submitted on 2021-01-11. Permission was granted on 2021-03-04, 2 months later. The site became operational on 2021-11-10, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8405.