Novarly ParcelRenewable sites

Renewable sitesBredbury Park Way - AD Stockport (Waste AD)

Bredbury Park Way - AD Stockport (Waste AD)

Bredbury Park Way - AD Stockport (Waste AD) is an operational 2 MW anaerobic digestion plant in Stockport, generating since 3 October 2011. Planning permission was granted on 2 November 2007, 3 months after submission. Operator of record: Greater Manchester Waste.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 3 October 2011
Anaerobic Digestion
Technology
Greater Manchester Waste
Stockport
Authority
England

Planning and build timeline

Application submitted6 August 2007
Permission granted2 November 2007
3 months after submission
Operational3 October 2011
47 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Stockport: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Bredbury Park Way - AD Stockport (Waste AD)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
49.91.9 km
Battery · Operational
201.9 km
Battery · Under Construction
49.92 km
Solar Photovoltaics · Operational
1.162.7 km
Solar Photovoltaics · Operational
0.274.6 km
Solar Photovoltaics · Operational
34.8 km
Solar Photovoltaics · Operational
0.75.5 km
Solar Photovoltaics · Operational
0.67.3 km

How big is Bredbury Park Way - AD Stockport (Waste AD)?

Bredbury Park Way - AD Stockport (Waste AD) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bredbury Park Way - AD Stockport (Waste AD)?

REPD records the operator as Greater Manchester Waste. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bredbury Park Way - AD Stockport (Waste AD) approved and built?

The application was submitted on 6 August 2007. Permission was granted on 2 November 2007, 3 months later. The site became operational on 3 October 2011, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 263.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode