Tesco Super-Store (Garratt Way, Gorton)

Tesco Super-Store (Garratt Way, Gorton) is an operational 0.7 MW solar farm in Manchester, generating since 1 July 2020. Planning permission was granted on 1 March 2019, 2 months after submission. Operator of record: Push Energy.

0.7 MW
Capacity
as recorded in REPD
Operational
Status
since 1 July 2020
Solar Photovoltaics
Technology
Push Energy
Manchester
Authority
England

Planning and build timeline

Application submitted2 January 2019
Permission granted1 March 2019
2 months after submission
Operational1 July 2020
16 months after consent

Screening a site of your own?

RedlineUK · £39

Manchester approves 91% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Tesco Super-Store (Garratt Way, Gorton)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Manchester’s record on solar

Manchester has decided 45 solar farms and approved 91%, taking a median of 1.7 months. See every solar farm decision in Manchester

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.61.9 km
Solar Photovoltaics · Under Construction
3.382.5 km
EfW Incineration · Operational
33.52.6 km
Solar Photovoltaics · Under Construction
0.922.8 km
Solar Photovoltaics · Operational
0.72.9 km
Solar Photovoltaics · Operational
1.163 km
Solar Photovoltaics · Under Construction
0.174.2 km
Anaerobic Digestion · Operational
24.7 km

How big is Tesco Super-Store (Garratt Way, Gorton)?

Tesco Super-Store (Garratt Way, Gorton) has a recorded installed capacity of 0.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tesco Super-Store (Garratt Way, Gorton)?

REPD records the operator as Push Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tesco Super-Store (Garratt Way, Gorton) approved and built?

The application was submitted on 2 January 2019. Permission was granted on 1 March 2019, 2 months later. The site became operational on 1 July 2020, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7292.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode