Renewable sites › Bower Park Academy - Solar Photovoltaic Panels
Bower Park Academy - Solar Photovoltaic Panels
Bower Park Academy - Solar Photovoltaic Panels is operational in Havering with a recorded capacity of 0.26 MW, and has been generating since 2021-12-26.
Planning and build timeline
| Application submitted | 2021-01-07 |
| Permission granted | 2021-10-08 9 months after submission |
| Operational | 2021-12-26 3 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Havering
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Havering’s record on solar
Havering has decided 10 solar farms and approved 80%, taking a median of 2.8 months. See every solar farm decision in Havering →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Cranham Golf Course Solar Park Solar Photovoltaics · Operational | 2.6 | 8.7 km |
Ford Motor Company Ltd (Extension) Wind Onshore · Operational | 2 | 8.8 km |
Dagenham Docks Biogas (Waste AD) Anaerobic Digestion · Operational | 1.4 | 9.6 km |
East Dagenham Docks AD (AD) Anaerobic Digestion · Operational | 1.4 | 9.8 km |
Clay Tye Farm Phase 1 - Storage Facility Battery · Operational | 49.5 | 9.9 km |
Clay Tye Farm Phase 2 - Storage Facility Battery · Operational | 49.5 | 9.9 km |
Ford Wind Park - Dagenham Wind Onshore · Operational | 5.9 | 9.9 km |
Riverside Sewage Treatment Works Digestion Plant Sewage Sludge Digestion · Operational | 4 | 9.9 km |
How big is Bower Park Academy - Solar Photovoltaic Panels?
Bower Park Academy - Solar Photovoltaic Panels has a recorded installed capacity of 0.26 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bower Park Academy - Solar Photovoltaic Panels?
REPD records the operator as London Borough of Hounslow. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bower Park Academy - Solar Photovoltaic Panels approved and built?
The application was submitted on 2021-01-07. Permission was granted on 2021-10-08, 9 months later. The site became operational on 2021-12-26, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9351.