Renewable sites › Clay Tye Farm Phase 2 - Storage Facility
Clay Tye Farm Phase 2 - Storage Facility
Clay Tye Farm Phase 2 - Storage Facility is operational in Havering with a recorded capacity of 49.5 MW, and has been generating since 2024-03-22.
Planning and build timeline
| Application submitted | 2018-06-13 |
| Permission granted | 2020-02-05 20 months after submission |
| Operational | 2024-03-22 50 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Havering
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Clay Tye Farm Phase 1 - Storage Facility Battery · Operational | 49.5 | 0 km |
Cranham Golf Course Solar Park Solar Photovoltaics · Operational | 2.6 | 1.1 km |
Fen Lane, Bulphan Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 2.3 km |
Ockendon Landfill Solar Farm Solar Photovoltaics · Operational | 38 | 3.3 km |
Ockendon Area III Landfill Gas · Operational | 8.5 | 3.4 km |
Bulphan Fen Solar Farm & Battery Storage Solar Photovoltaics · Under Construction | 49.9 | 3.5 km |
Bulphan Fen Solar Farm & Battery Storage Battery · Under Construction | — | 3.5 km |
Little Belhus Restoration Site Wind Onshore · Operational | 1 | 3.5 km |
How big is Clay Tye Farm Phase 2 - Storage Facility?
Clay Tye Farm Phase 2 - Storage Facility has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clay Tye Farm Phase 2 - Storage Facility?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clay Tye Farm Phase 2 - Storage Facility approved and built?
The application was submitted on 2018-06-13. Permission was granted on 2020-02-05, 20 months later. The site became operational on 2024-03-22, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11721.