Renewable sites › Clay Tye Farm Phase 2 - Storage Facility
Clay Tye Farm Phase 2 - Storage Facility
Clay Tye Farm Phase 2 - Storage Facility is an operational 49.5 MW battery storage site in Havering, generating since 22 March 2024. Planning permission was granted on 5 February 2020, 20 months after submission. Operator of record: Harmony Energy Storage.
Planning and build timeline
| Application submitted | 13 June 2018 |
| Permission granted | 5 February 2020 20 months after submission |
| Operational | 22 March 2024 50 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Havering: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Clay Tye Farm Phase 2 - Storage Facility’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Havering
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 49.5 | 0 km |
Solar Photovoltaics · Operational | 2.6 | 1.1 km |
Solar Photovoltaics · Under Construction | 49.9 | 2.3 km |
Solar Photovoltaics · Operational | 38 | 3.3 km |
Landfill Gas · Operational | 8.5 | 3.4 km |
Battery · Under Construction | — | 3.5 km |
Solar Photovoltaics · Under Construction | 49.9 | 3.5 km |
Wind Onshore · Operational | 1 | 3.5 km |
How big is Clay Tye Farm Phase 2 - Storage Facility?
Clay Tye Farm Phase 2 - Storage Facility has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Clay Tye Farm Phase 2 - Storage Facility?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Clay Tye Farm Phase 2 - Storage Facility approved and built?
The application was submitted on 13 June 2018. Permission was granted on 5 February 2020, 20 months later. The site became operational on 22 March 2024, 50 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11721.