Canopus Farm

Canopus Farm is operational in East Lindsey with a recorded capacity of 5 MW, and has been generating since 2015-12-10.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-10
Solar Photovoltaics
Technology
Countryside Renewables
East Lindsey
Authority
England

Planning and build timeline

Application submitted2015-01-05
Permission granted2015-03-26
3 months after submission
Operational2015-12-10
9 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Lindsey’s record on solar

East Lindsey has decided 28 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in East Lindsey

Other built sites within 15 km

SiteMWDistance
Fen Road
Solar Photovoltaics · Operational
1.45 km
Pinguin Foods
Solar Photovoltaics · Operational
1.55.5 km
Marsh Lane - Solar PV Panels
Solar Photovoltaics · Under Construction
0.895.9 km
Staples Anaerobic Digestion CHP Plant (Waste AD)
Anaerobic Digestion · Operational
1.46.4 km
Riverside Industrial Estate Gasification Plant
Advanced Conversion Technologies · Operational
10.56.5 km
Carrington Farm AD
Anaerobic Digestion · Operational
36.8 km
Boston Landfill, Wyberton - Solar PV Array
Solar Photovoltaics · Under Construction
9.77.1 km
Boston Landfill Scheme
Landfill Gas · Operational
1.37.6 km

How big is Canopus Farm?

Canopus Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Canopus Farm?

REPD records the operator as Countryside Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Canopus Farm approved and built?

The application was submitted on 2015-01-05. Permission was granted on 2015-03-26, 3 months later. The site became operational on 2015-12-10, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4951.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council