Novarly ParcelRenewable sites

Renewable sitesBolton TRF

Bolton TRF

Bolton TRF is operational in Bolton with a recorded capacity of 10.8 MW, and has been generating since 2001-06-01.

10.8 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-06-01
EfW Incineration
Technology
Viridor (GMWDA)
Bolton
Authority
England

Planning and build timeline

Application submitted1996-12-16
Permission granted1997-05-30
5 months after submission
Operational2001-06-01
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Salford Road
Solar Photovoltaics · Operational
1.61.9 km
Salford Road Solar Farm
Solar Photovoltaics · Operational
2.24 km
Bent Spur Solar Farm
Solar Photovoltaics · Operational
54.3 km
Kenyon Way
Solar Photovoltaics · Under Construction
1.94.9 km
Tesco Crab Tree Lane
Solar Photovoltaics · Operational
0.57.3 km
Atherton - Battery energy storage
Battery · Operational
307.8 km
Clifton Hall
Landfill Gas · Operational
18 km
Lascar Works
Battery · Operational
208.2 km

How big is Bolton TRF?

Bolton TRF has a recorded installed capacity of 10.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bolton TRF?

REPD records the operator as Viridor (GMWDA). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bolton TRF approved and built?

The application was submitted on 1996-12-16. Permission was granted on 1997-05-30, 5 months later. The site became operational on 2001-06-01, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 898.