Renewable sites › Atherton - Battery energy storage
Atherton - Battery energy storage
Atherton - Battery energy storage is operational in Wigan with a recorded capacity of 30 MW, and has been generating since 2025-09-10.
Planning and build timeline
| Application submitted | 2022-02-15 |
| Permission granted | 2022-07-29 5 months after submission |
| Operational | 2025-09-10 37 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Tesco Crab Tree Lane Solar Photovoltaics · Operational | 0.5 | 1.1 km |
Salford Road Solar Farm Solar Photovoltaics · Operational | 2.2 | 3.9 km |
Kenyon Way Solar Photovoltaics · Under Construction | 1.9 | 4.4 km |
Whitehead Landfill Landfill Gas · Operational | 5.3 | 5.3 km |
Kirkless Power Landfill Gas · Operational | 2.1 | 6.2 km |
Bolton TRF EfW Incineration · Operational | 10.8 | 7.8 km |
Salford Road Solar Photovoltaics · Operational | 1.6 | 7.8 km |
Bent Spur Solar Farm Solar Photovoltaics · Operational | 5 | 8.5 km |
How big is Atherton - Battery energy storage?
Atherton - Battery energy storage has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Atherton - Battery energy storage?
REPD records the operator as FPC Electric Land Limited / Pulse Clean Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Atherton - Battery energy storage approved and built?
The application was submitted on 2022-02-15. Permission was granted on 2022-07-29, 5 months later. The site became operational on 2025-09-10, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11151.