Renewable sites › Blackstone Edge
Blackstone Edge
Blackstone Edge is operational in Barnsley with a recorded capacity of 7.5 MW, and has been generating since 2013-03-01.
Planning and build timeline
| Application submitted | 2006-11-01 |
| Permission granted | 2009-05-26 31 months after submission |
| Operational | 2013-03-01 45 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
- Green Belt — Barnsley
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Barnsley’s record on onshore wind
Barnsley has decided 7 onshore wind schemes and approved 71%, taking a median of 8.6 months. See every onshore wind scheme decision in Barnsley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Spicer Hill Wind Farm Wind Onshore · Operational | 6.9 | 1.2 km |
Hazlehead Wind Onshore · Operational | 6 | 2.1 km |
Royd Moor Wind Onshore · Operational | 5.9 | 2.7 km |
Barnsley 1.5 Biomass (dedicated) · Operational | 9 | 13 km |
Vine Street EfW EfW Incineration · Operational | 9.5 | 13.5 km |
United Anodisers, Red Doles Lane - Solar Panels Solar Photovoltaics · Under Construction | 0.31 | 13.7 km |
How big is Blackstone Edge?
Blackstone Edge has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Blackstone Edge?
REPD records the operator as Ventient (formerly Infinis). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Blackstone Edge approved and built?
The application was submitted on 2006-11-01. Permission was granted on 2009-05-26, 31 months later. The site became operational on 2013-03-01, 45 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3958.