Novarly ParcelRenewable planning

Renewable planning Onshore windBarnsley

Onshore wind planning in Barnsley

Barnsley has decided 7 onshore wind schemes and approved 71% of them, taking a median of 8.6 months to decide. Consented capacity: 35 MW.

71%
Approved
5 granted · 2 refused
8.6 mo
Median decision
UK 11.5 mo
35 MW
Consented
10 MW refused
1
Appeals
0 allowed on appeal

⚠️ Small caseload (7 decided). Percentages here move a lot with one more decision — read them as indicative, not as a reliable rate.

How Barnsley compares

Against the 75 UK authorities with 5+ onshore wind decisions, Barnsley sits in the 57th percentile for approval rate (3 points above the England average) and the 82nd percentile for speed.

Decisions by year

35Approved — 1 (2010)110Approved — 1 (2014)114Refused — 1 (2015)115
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (7)

SchemeMWStatusDecided
Spicer Hill Wind Farm Extension
JG Pears Power · 2014/1442 · 3 mo to decide
6.9Appeal Refused2015-02-23
Park Spring Wind Farm
EDF Energy Renewables · 2013/0860 · 6 mo to decide
8.6Operational2014-04-09
Spicer Hill Wind Farm
J G Pears Limited · 2009/0572 · 11.1 mo to decide
6.9Operational2010-04-01
Blackstone Edge
Ventient (formerly Infinis) · 2008/0171 · 30.8 mo to decide
7.5Operational2009-05-26
Hazlehead
Banks Renewables · 2006/1575 · 6 mo to decide
6Operational2007-03-08
Hepworth Clay Pipeworks Wind Farm
Hepworth Building Products Limited · 29.1 mo to decide
3.4Application Refused1996-12-03
Royd Moor
Unknown
5.9Operational

Does Barnsley approve onshore wind schemes?

Yes — of the 7 onshore wind schemes Barnsley has decided, 71% were approved (5 granted, 2 refused). The UK-wide rate for onshore wind is 68%. Note this is a small caseload, so treat the percentage as indicative rather than statistically robust.

How long does a onshore wind scheme application take in Barnsley?

The median time from application to decision is 8.6 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Barnsley consented?

35 MW has been consented across 5 approved schemes, with 10 MW refused. There are no applications currently awaiting a decision.

Other technologies in Barnsley

Solar in BarnsleyBattery storage in Barnsley

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report