Renewable sites › Brochloch Rig (formerly Windy Standard II)
Brochloch Rig (formerly Windy Standard II)
Brochloch Rig (formerly Windy Standard II) is an operational 90 MW onshore wind farm in Scotland, generating since 15 June 2017. Planning permission was granted on 13 March 2007, 63 months after submission. Operator of record: Fred Olsen Renewables.
Planning and build timeline
| Application submitted | 14 December 2001 |
| Permission granted | 13 March 2007 63 months after submission |
| Operational | 15 June 2017 123 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Brochloch Rig (formerly Windy Standard II)’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 21.6 | 1.4 km |
Wind Onshore · Operational | 43 | 2.5 km |
Wind Onshore · Operational | 50 | 2.8 km |
Wind Onshore · Under Construction | 87.6 | 3 km |
Wind Onshore · Operational | 240 | 6.4 km |
Wind Onshore · Under Construction | 70 | 7.4 km |
Wind Onshore · Operational | 67.1 | 7.5 km |
Wind Onshore · Under Construction | 308 | 8.5 km |
How big is Brochloch Rig (formerly Windy Standard II)?
Brochloch Rig (formerly Windy Standard II) has a recorded installed capacity of 90 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brochloch Rig (formerly Windy Standard II)?
REPD records the operator as Fred Olsen Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brochloch Rig (formerly Windy Standard II) approved and built?
The application was submitted on 14 December 2001. Permission was granted on 13 March 2007, 63 months later. The site became operational on 15 June 2017, 123 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4431.