Renewable sitesTorrs Hill

Torrs Hill

Torrs Hill is a 4 MW onshore wind farm under construction in Dumfries and Galloway. Planning permission was granted on 23 March 2004, 9 months after submission. Operator of record: Torrs Hill Windfarm Ltd.

4 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Wind Onshore
Technology
Torrs Hill Windfarm Ltd
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted9 June 2003
Permission granted23 March 2004
9 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Torrs Hill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
67.110.5 km
Wind Onshore · Under Construction
87.612.4 km
Wind Onshore · Operational
4314.3 km

How big is Torrs Hill?

Torrs Hill has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Torrs Hill?

REPD records the operator as Torrs Hill Windfarm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Torrs Hill approved and built?

The application was submitted on 9 June 2003. Permission was granted on 23 March 2004, 9 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4529.