Novarly ParcelRenewable sites

Renewable sitesTurncole Wind Farm

Turncole Wind Farm

Turncole Wind Farm is operational in Maldon with a recorded capacity of 17.5 MW, and has been generating since 2016-12-22.

17.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-12-22
Wind Onshore
Technology
RES/ Aviva
Maldon
Authority
England

Planning and build timeline

Application submitted2011-06-30
Permission granted2014-02-14
32 months after submission
Operational2016-12-22
34 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Middlewick wind farm
Wind Onshore · Operational
20.72.1 km
Wick Farm (Burnham on Crouch)
Solar Photovoltaics · Operational
53.2 km
Bradwell Wind Farm (Repower)
Wind Onshore · Operational
207.3 km
Barling Hall Farm
Landfill Gas · Operational
2.49.5 km
Fambridge Road/Canewdon Road
Solar Photovoltaics · Operational
512.3 km
South Fambridge Hall - Solar farm & Battery storage
Solar Photovoltaics · Under Construction
49.9912.7 km
South Fambridge Hall - Solar farm & Battery storage
Battery · Under Construction
2012.7 km
London Southend Airport
Solar Photovoltaics · Operational
2.514.7 km

How big is Turncole Wind Farm?

Turncole Wind Farm has a recorded installed capacity of 17.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Turncole Wind Farm?

REPD records the operator as RES/ Aviva. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Turncole Wind Farm approved and built?

The application was submitted on 2011-06-30. Permission was granted on 2014-02-14, 32 months later. The site became operational on 2016-12-22, 34 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4067.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council