Renewable sites › Ark Hill
Ark Hill
Ark Hill is operational in Angus with a recorded capacity of 6.4 MW, and has been generating since 2013-03-29.
Planning and build timeline
| Application submitted | 2003-07-07 |
| Permission granted | 2006-06-15 35 months after submission |
| Operational | 2013-03-29 81 months after consent |
Angus’s record on onshore wind
Angus has decided 17 onshore wind schemes and approved 12%, taking a median of 10.2 months. See every onshore wind scheme decision in Angus →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Dunsinane Industrial Estate Battery · Operational | 49.9 | 10.3 km |
Dundee Technology Park Battery · Operational | 49.9 | 11 km |
Dragonhall Farm, Padanaram - Battery Storage Battery · Under Construction | 10 | 11.4 km |
Dragonhall Farm, Padanaram - Solar Photovoltaic Array Solar Photovoltaics · Under Construction | 5 | 11.4 km |
Drumderg Wind Onshore · Operational | 36.8 | 12.7 km |
Baldovie EfW Incineration · Operational | 8.3 | 13 km |
Harris Academy, Perth Road - Extension/Roof Solar Photovoltaic Array Solar Photovoltaics · Under Construction | — | 13 km |
Baldovie Industrial Estate (Forties Road) EfW Incineration · Under Construction | 10 | 13.2 km |
How big is Ark Hill?
Ark Hill has a recorded installed capacity of 6.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ark Hill?
REPD records the operator as Green Cat Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ark Hill approved and built?
The application was submitted on 2003-07-07. Permission was granted on 2006-06-15, 35 months later. The site became operational on 2013-03-29, 81 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4062.
Novarly Parcel · official public data, read properly · parcel.novarly.com