Renewable sitesAvonmouth Port

Avonmouth Port

Avonmouth Port is an operational 6 MW onshore wind farm in Bristol, City of, generating since 20 August 2007. Planning permission was granted on 16 December 2005, 4 months after submission. Operator of record: Bristol Port Authority.

6 MW
Capacity
as recorded in REPD
Operational
Status
since 20 August 2007
Wind Onshore
Technology
Bristol Port Authority
Bristol, City of
Authority
England

Planning and build timeline

Application submitted8 August 2005
Permission granted16 December 2005
4 months after submission
Operational20 August 2007
20 months after consent

Screening a site of your own?

RedlineUK · £39

Bristol, City of approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Avonmouth Port’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Bristol, City of’s record on onshore wind

Bristol, City of has decided 6 onshore wind schemes and approved 100%, taking a median of 4.5 months. See every onshore wind scheme decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Advanced Conversion Technologies · Operational
6.51.1 km
Advanced Conversion Technologies · Operational
6.51.1 km
Wind Onshore · Operational
2.51.2 km
Wind Onshore · Operational
91.3 km
Solar Photovoltaics · Operational
4.22 km
Wind Onshore · Operational
8.22.3 km
Anaerobic Digestion · Operational
102.5 km
Battery · Operational
323.2 km

How big is Avonmouth Port?

Avonmouth Port has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Avonmouth Port?

REPD records the operator as Bristol Port Authority. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Avonmouth Port approved and built?

The application was submitted on 8 August 2005. Permission was granted on 16 December 2005, 4 months later. The site became operational on 20 August 2007, 20 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3194.