Renewable sites › Bristol STW (Waste AD)
Bristol STW (Waste AD)
Bristol STW (Waste AD) is operational in Bristol, City of with a recorded capacity of 10 MW, and has been generating since 2012-12-04.
Planning and build timeline
| Application submitted | 2010-06-11 |
| Permission granted | 2010-12-14 6 months after submission |
| Operational | 2012-12-04 24 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Avonmouth Wind Power Wind Onshore · Operational | 8.2 | 0.3 km |
Avonmouth Solar Photovoltaics · Operational | 4.2 | 0.8 km |
Moorhouse Lane Solar Photovoltaics · Operational | 1.8 | 0.9 km |
Severn Road Battery · Operational | 32 | 0.9 km |
Moorhouse Farm, Moorhouse Lane - Solar Park Solar Photovoltaics · Under Construction | 3.81 | 0.9 km |
Accolade Wines Wind Onshore · Operational | 2.5 | 1.4 km |
Avonmouth Low Carbon Energy Facility - Phase 2 Advanced Conversion Technologies · Operational | 6.5 | 1.5 km |
Avonmouth Advanced Conversion Technologies · Operational | 6.5 | 1.5 km |
How big is Bristol STW (Waste AD)?
Bristol STW (Waste AD) has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bristol STW (Waste AD)?
REPD records the operator as GENeco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bristol STW (Waste AD) approved and built?
The application was submitted on 2010-06-11. Permission was granted on 2010-12-14, 6 months later. The site became operational on 2012-12-04, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 232.