Renewable sites › Avonmouth Low Carbon Energy Facility - Phase 2
Avonmouth Low Carbon Energy Facility - Phase 2
Avonmouth Low Carbon Energy Facility - Phase 2 is an operational 6.5 MW advanced conversion plant in Bristol, City of, generating since 30 December 2013. Planning permission was granted on 18 October 2010, 4 months after submission. Operator of record: Avonmouth Biopower.
Planning and build timeline
| Application submitted | 30 June 2010 |
| Permission granted | 18 October 2010 4 months after submission |
| Operational | 30 December 2013 38 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Bristol, City of: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Avonmouth Low Carbon Energy Facility - Phase 2’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Advanced Conversion Technologies · Operational | 6.5 | 0 km |
Wind Onshore · Operational | 2.5 | 0.8 km |
Solar Photovoltaics · Operational | 4.2 | 0.9 km |
Wind Onshore · Operational | 9 | 0.9 km |
Wind Onshore · Operational | 6 | 1.1 km |
Wind Onshore · Operational | 8.2 | 1.2 km |
Anaerobic Digestion · Operational | 10 | 1.5 km |
Battery · Operational | 32 | 2.3 km |
How big is Avonmouth Low Carbon Energy Facility - Phase 2?
Avonmouth Low Carbon Energy Facility - Phase 2 has a recorded installed capacity of 6.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Avonmouth Low Carbon Energy Facility - Phase 2?
REPD records the operator as Avonmouth Biopower. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Avonmouth Low Carbon Energy Facility - Phase 2 approved and built?
The application was submitted on 30 June 2010. Permission was granted on 18 October 2010, 4 months later. The site became operational on 30 December 2013, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1014.