Renewable sitesSevern Road

Severn Road

Severn Road is an operational 32 MW battery storage site in Bristol, City of, generating since 23 December 2021. Planning permission was granted on 21 February 2018, 5 months after submission. Operator of record: FPC Industry & Enterprise.

32 MW
Capacity
as recorded in REPD
Operational
Status
since 23 December 2021
Battery
Technology
FPC Industry & Enterprise
Bristol, City of
Authority
England

Planning and build timeline

Application submitted5 October 2017
Permission granted21 February 2018
5 months after submission
Operational23 December 2021
46 months after consent

Screening a site of your own?

RedlineUK · £39

Bristol, City of approves 100% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Severn Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bristol, City of’s record on battery storage

Bristol, City of has decided 8 battery storage schemes and approved 100%, taking a median of 2.3 months. See every battery storage scheme decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
1.80.4 km
Solar Photovoltaics · Under Construction
3.810.5 km
Anaerobic Digestion · Operational
100.9 km
Wind Onshore · Operational
8.21.2 km
EfW Incineration · Operational
341.3 km
Solar Photovoltaics · Operational
1.81.7 km
Solar Photovoltaics · Operational
4.21.7 km
Wind Onshore · Operational
2.52 km

How big is Severn Road?

Severn Road has a recorded installed capacity of 32 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Severn Road?

REPD records the operator as FPC Industry & Enterprise. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Severn Road approved and built?

The application was submitted on 5 October 2017. Permission was granted on 21 February 2018, 5 months later. The site became operational on 23 December 2021, 46 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7085.