Avonmouth Port - extension is an operational 9 MW onshore wind farm in Bristol, City of, generating since 1 April 2014. Planning permission was granted on 14 October 2010, 5 months after submission. Operator of record: Bristol Port Company.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 1 April 2014
Wind Onshore
Technology
Bristol Port Company
Bristol, City of
Authority
England

Planning and build timeline

Application submitted12 May 2010
Permission granted14 October 2010
5 months after submission
Operational1 April 2014
42 months after consent

Screening a site of your own?

RedlineUK · £39

Bristol, City of approves 100% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Avonmouth Port - extension’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bristol, City of’s record on onshore wind

Bristol, City of has decided 6 onshore wind schemes and approved 100%, taking a median of 4.5 months. See every onshore wind scheme decision in Bristol, City of

Other built sites within 15 km

SiteMWDistance
Advanced Conversion Technologies · Operational
6.50.9 km
Advanced Conversion Technologies · Operational
6.50.9 km
Wind Onshore · Operational
61.3 km
Solar Photovoltaics · Operational
4.21.5 km
Wind Onshore · Operational
2.51.7 km
Wind Onshore · Operational
8.22 km
Anaerobic Digestion · Operational
102.3 km
Solar Photovoltaics · Operational
1.83.2 km

How big is Avonmouth Port - extension?

Avonmouth Port - extension has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Avonmouth Port - extension?

REPD records the operator as Bristol Port Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Avonmouth Port - extension approved and built?

The application was submitted on 12 May 2010. Permission was granted on 14 October 2010, 5 months later. The site became operational on 1 April 2014, 42 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4159.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode