Renewable sites › Mark Hill
Mark Hill
Mark Hill is an operational 56 MW onshore wind farm in Scotland, generating since 1 June 2011. Planning permission was granted on 1 June 2008, 33 months after submission. Operator of record: Force 9 Energy.
Planning and build timeline
| Application submitted | 19 August 2005 |
| Permission granted | 1 June 2008 33 months after submission |
| Operational | 1 June 2011 36 months after consent |
Screening a site of your own?
Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Mark Hill’s recorded coordinate — swap in your own postcode or coordinates.
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 20 | 7.4 km |
Wind Onshore · Operational | 120 | 7.4 km |
Wind Onshore · Under Construction | 72.8 | 7.4 km |
Wind Onshore · Operational | 25 | 11.1 km |
Wind Onshore · Operational | 42 | 11.9 km |
Wind Onshore · Operational | 20 | 14 km |
Wind Onshore · Operational | 120 | 14.3 km |
Wind Onshore · Under Construction | 50.4 | 15 km |
How big is Mark Hill?
Mark Hill has a recorded installed capacity of 56 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Mark Hill?
REPD records the operator as Force 9 Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Mark Hill approved and built?
The application was submitted on 19 August 2005. Permission was granted on 1 June 2008, 33 months later. The site became operational on 1 June 2011, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3260.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode