Novarly ParcelRenewable sites

Renewable sitesWythegill Wind Turbine

Wythegill Wind Turbine

Wythegill Wind Turbine is an operational 2.3 MW onshore wind farm in Cumberland, generating since 15 June 2015. Planning permission was granted on 11 October 2012, 18 months after submission. Operator of record: Airvolution Energy.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 15 June 2015
Wind Onshore
Technology
Airvolution Energy
Cumberland
Authority
England

Planning and build timeline

Application submitted14 April 2011
Permission granted11 October 2012
18 months after submission
Operational15 June 2015
32 months after consent

Screening a site of your own?

RedlineUK · £39

Cumberland approves 66% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wythegill Wind Turbine’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cumberland’s record on onshore wind

Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
50.2 km
Wind Onshore · Operational
41.1 km
Wind Onshore · Operational
4.21.3 km
Wind Onshore · Operational
6.21.6 km
Biomass (dedicated) · Operational
491.9 km
Wind Onshore · Operational
5.42.7 km
Wind Onshore · Operational
63.9 km
Wind Onshore · Operational
8.85.2 km

How big is Wythegill Wind Turbine?

Wythegill Wind Turbine has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Wythegill Wind Turbine?

REPD records the operator as Airvolution Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wythegill Wind Turbine approved and built?

The application was submitted on 14 April 2011. Permission was granted on 11 October 2012, 18 months later. The site became operational on 15 June 2015, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3832.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode