Renewable sites › Eastman Chemicals, Workington
Eastman Chemicals, Workington
Eastman Chemicals, Workington is operational in Cumberland with a recorded capacity of 4 MW, and has been generating since 2006-10-01.
Planning and build timeline
| Application submitted | 2003-06-24 |
| Permission granted | 2003-09-08 2 months after submission |
| Operational | 2006-10-01 37 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on onshore wind
Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Siddick Wind Farm Wind Onshore · Operational | 4.2 | 0.4 km |
Iggesund Paperboard CHP Plant Biomass (dedicated) · Operational | 49 | 0.9 km |
St Helen's Lane Solar Photovoltaics · Operational | 5 | 1 km |
Wythegill Wind Turbine Wind Onshore · Operational | 2.3 | 1.1 km |
Oldside Wind Farm Wind Onshore · Operational | 5.4 | 1.7 km |
Land at Flimby Hall Farm Wind Onshore · Operational | 6.2 | 2.4 km |
Winscales Moor Wind Onshore · Operational | 6 | 4.3 km |
Winscales Phase I and II Wind Onshore · Operational | 8.8 | 5.3 km |
How big is Eastman Chemicals, Workington?
Eastman Chemicals, Workington has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Eastman Chemicals, Workington?
REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Eastman Chemicals, Workington approved and built?
The application was submitted on 2003-06-24. Permission was granted on 2003-09-08, 2 months later. The site became operational on 2006-10-01, 37 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2935.