Iggesund Paperboard CHP Plant
Iggesund Paperboard CHP Plant is operational in Cumberland with a recorded capacity of 49 MW, and has been generating since 2013-02-17.
Planning and build timeline
| Application submitted | 2010-11-17 |
| Permission granted | 2011-03-08 4 months after submission |
| Operational | 2013-02-17 23 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Oldside Wind Farm Wind Onshore · Operational | 5.4 | 0.8 km |
Eastman Chemicals, Workington Wind Onshore · Operational | 4 | 0.9 km |
Siddick Wind Farm Wind Onshore · Operational | 4.2 | 1.2 km |
St Helen's Lane Solar Photovoltaics · Operational | 5 | 1.8 km |
Wythegill Wind Turbine Wind Onshore · Operational | 2.3 | 1.9 km |
Land at Flimby Hall Farm Wind Onshore · Operational | 6.2 | 3.4 km |
Winscales Moor Wind Onshore · Operational | 6 | 4.1 km |
Winscales Phase I and II Wind Onshore · Operational | 8.8 | 4.8 km |
How big is Iggesund Paperboard CHP Plant?
Iggesund Paperboard CHP Plant has a recorded installed capacity of 49 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Iggesund Paperboard CHP Plant?
REPD records the operator as Iggesund Paperboard (Workington). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Iggesund Paperboard CHP Plant approved and built?
The application was submitted on 2010-11-17. Permission was granted on 2011-03-08, 4 months later. The site became operational on 2013-02-17, 23 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 47.