Renewable sites › Land at Flimby Hall Farm
Land at Flimby Hall Farm
Land at Flimby Hall Farm is operational in Cumberland with a recorded capacity of 6.2 MW, and has been generating since 2013-06-14.
Planning and build timeline
| Application submitted | 2009-06-09 |
| Permission granted | 2010-06-18 12 months after submission |
| Operational | 2013-06-14 36 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cumberland’s record on onshore wind
Cumberland has decided 38 onshore wind schemes and approved 66%, taking a median of 10.3 months. See every onshore wind scheme decision in Cumberland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wythegill Wind Turbine Wind Onshore · Operational | 2.3 | 1.6 km |
St Helen's Lane Solar Photovoltaics · Operational | 5 | 1.6 km |
Siddick Wind Farm Wind Onshore · Operational | 4.2 | 2.4 km |
Eastman Chemicals, Workington Wind Onshore · Operational | 4 | 2.4 km |
Iggesund Paperboard CHP Plant Biomass (dedicated) · Operational | 49 | 3.4 km |
Oldside Wind Farm Wind Onshore · Operational | 5.4 | 4.1 km |
Winscales Moor Wind Onshore · Operational | 6 | 5.1 km |
Winscales Phase I and II Wind Onshore · Operational | 8.8 | 6.5 km |
How big is Land at Flimby Hall Farm?
Land at Flimby Hall Farm has a recorded installed capacity of 6.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land at Flimby Hall Farm?
REPD records the operator as Flimby Wind Energy Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land at Flimby Hall Farm approved and built?
The application was submitted on 2009-06-09. Permission was granted on 2010-06-18, 12 months later. The site became operational on 2013-06-14, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3972.