Renewable sites › Worksop - B&Q
Worksop - B&Q
Worksop - B&Q is operational in Bassetlaw with a recorded capacity of 2 MW, and has been generating since 2009-01-21.
Planning and build timeline
| Application submitted | 2007-09-07 |
| Permission granted | 2007-11-01 2 months after submission |
| Operational | 2009-01-21 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bassetlaw’s record on onshore wind
Bassetlaw has decided 5 onshore wind schemes and approved 40%, taking a median of 12.4 months. See every onshore wind scheme decision in Bassetlaw →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Walkers Wood Solar Park Solar Photovoltaics · Operational | 27 | 5.3 km |
Little Morton Solar Farm Solar Photovoltaics · Operational | 14.3 | 5.5 km |
Welbeck Solar / Hazel Gap Solar Photovoltaics · Operational | 16 | 6.9 km |
Netherfield Lane Solar Photovoltaics · Operational | 19.7 | 7.7 km |
Jubilee Farm, Barnby Moor Solar Photovoltaics · Operational | 5 | 7.9 km |
Barnby Moor Solar Photovoltaics · Operational | 4 | 8.3 km |
Hunciecroft Farm Solar Photovoltaics · Operational | 8 | 8.7 km |
Welbeck Colliery Solar Photovoltaics · Operational | 11.3 | 9.4 km |
How big is Worksop - B&Q?
Worksop - B&Q has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Worksop - B&Q?
REPD records the operator as Ecotricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Worksop - B&Q approved and built?
The application was submitted on 2007-09-07. Permission was granted on 2007-11-01, 2 months later. The site became operational on 2009-01-21, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3510.