Renewable sites › Welbeck Solar / Hazel Gap
Welbeck Solar / Hazel Gap
Welbeck Solar / Hazel Gap is operational in Bassetlaw with a recorded capacity of 16 MW, and has been generating since 2015-03-19.
Planning and build timeline
| Application submitted | 2014-08-14 |
| Permission granted | 2015-01-09 5 months after submission |
| Operational | 2015-03-19 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bassetlaw’s record on solar
Bassetlaw has decided 23 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Bassetlaw →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Netherfield Lane Solar Photovoltaics · Operational | 19.7 | 1.5 km |
Welbeck Colliery Solar Photovoltaics · Operational | 11.3 | 2.7 km |
Hunciecroft Farm Solar Photovoltaics · Operational | 8 | 5.8 km |
Creswell Solar Park Solar Photovoltaics · Operational | 5 | 6.9 km |
Land South Off Ollerton Road Solar Photovoltaics · Operational | 4.2 | 6.9 km |
Worksop - B&Q Wind Onshore · Operational | 2 | 6.9 km |
SPF Thirty Acres Farm Solar Photovoltaics · Operational | 3.8 | 7.1 km |
Rufford Lane Solar Photovoltaics · Operational | 2.6 | 8.9 km |
How big is Welbeck Solar / Hazel Gap?
Welbeck Solar / Hazel Gap has a recorded installed capacity of 16 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Welbeck Solar / Hazel Gap?
REPD records the operator as Solar century / Magnetar Solar. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Welbeck Solar / Hazel Gap approved and built?
The application was submitted on 2014-08-14. Permission was granted on 2015-01-09, 5 months later. The site became operational on 2015-03-19, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2260.