Renewable sitesBarnby Moor

Barnby Moor

Barnby Moor is an operational 4 MW solar farm in Bassetlaw, generating since 30 March 2015. Planning permission was granted on 3 February 2014, 3 months after submission. Operator of record: Lark Energy.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 30 March 2015
Solar Photovoltaics
Technology
Lark Energy
Bassetlaw
Authority
England

Planning and build timeline

Application submitted15 November 2013
Permission granted3 February 2014
3 months after submission
Operational30 March 2015
14 months after consent

Screening a site of your own?

RedlineUK · £39

Bassetlaw approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Barnby Moor’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Bassetlaw’s record on solar

Bassetlaw has decided 23 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in Bassetlaw

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
32.5 km
Solar Photovoltaics · Operational
52.7 km
Solar Photovoltaics · Under Construction
49.93.7 km
Solar Photovoltaics · Operational
84.5 km
Solar Photovoltaics · Operational
1.74.6 km
Solar Photovoltaics · Operational
274.9 km
Solar Photovoltaics · Operational
14.35.8 km
Solar Photovoltaics · Operational
47.8 km

How big is Barnby Moor?

Barnby Moor has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barnby Moor?

REPD records the operator as Lark Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barnby Moor approved and built?

The application was submitted on 15 November 2013. Permission was granted on 3 February 2014, 3 months later. The site became operational on 30 March 2015, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1404.